Cangzhou China Railway Equipment Manufacturing Materials Co., Ltd. 180 Ton Dephosphorization Converter Project Environmental Impact Assessment Phase I Information Disclosure Content
Release time:
Mar 10,2018
Cangzhou China Railway Equipment Manufacturing Materials Co., Ltd. is built in the Bohai New District Industrial Zone of Cangzhou City. It was founded in 2007 and has formed a sintering capacity of 14.1 million tons/year, an ironmaking capacity of 7.5 million tons/year, and a steelmaking capacity of 7.2 million tons/year. The production capacity of hot rolling is 7.1 million tons/year.
1. Overview of construction project
Cangzhou China Railway Equipment Manufacturing Materials Co., Ltd. is built in Cangzhou Bohai New District Industrial Zone.007year, has now formed a sintering capacity1410million tons/Annual, ironmaking capacity750million tons/Annual, steelmaking capacity720million tons/Annual and hot rolling capacity710million tons/annual production capacity.
According to the company's overall product specification adjustment plan, plans to transform the steelmaking system, without increasing production capacity, improve product quality, add1 180tThe dephosphorization converter adopts the double smelting process to carry out the dephosphorization treatment of molten iron to improve the purity of the product and produce high quality steel grades.
2. Name and contact information of construction unit
Construction unit: Cangzhou China Railway Equipment Manufacturing Materials Co., Ltd.
Address: Bohai New District, Cangzhou, Hebei, China Zip Code:061113
Contact: Liu Hao
Contact number:0317-5761811
E-mail:czzthbb@163.com
3. Name and contact information of the environmental impact assessment institution undertaking the assessment work
Evaluation Unit: China Metallurgical Energy Conservation and Environmental Protection Co., Ltd.
Communication mode: Xitucheng Road, Haidian District, Beijing33No. Zip Code:100088
Contact: Mr. Liu
Contact number:010-82227664 Fax:010-82228597
E-mail:liushuang831022@sina.com
4, environmental impact assessment work procedures and main work content.
This EIA work is divided into three stages: preparation, on-site work, and report preparation.
Preparation stage: site survey, data collection, identification of environmental impact factors and screening of evaluation factors by the evaluation agency, determination of evaluation priorities and evaluation levels.
Site work phase: site investigation, supplementary data collection, environmental status monitoring and analogy investigation.
Report preparation stage: environmental quality status assessment, analysis of major environmental protection measures, environmental impact prediction and assessment; conduct public participation surveys, publicize simplified environmental impact reports, and prepare environmental impact reports.
5. Main matters for soliciting public opinions
The main purpose is to solicit public opinions and suggestions on environmental protection for the construction of this project, that is, the impact on your living environment and local environmental quality during and after the construction of this project, and the environmental protection measures taken to reduce the impact. The purpose is to further improve the environmental protection measures taken by the project, minimize the negative impact of the project construction, and safeguard the public interest.
6. Main ways of soliciting public opinions
Public comments or suggestions can be made from the date of publicity of the project.10Feedback to the construction unit or EIA unit by telephone, letter, fax, e-mail and other forms within 3 working days, and leave your contact information so that we can get in touch with you in time.
Hot Information
Mar 31,2022

Group office telephone:0317-5761108
Mailbox:sinogiant_office@163.com
cangzhou china railway company office telephone:0317-5761658
Mailbox:dangzhengban2012@126.com
feng south aspect of the company office telephone:0315-8530707
Mailbox:zhfngt@163.com
Scan code for more information